Updated for 2010 Changes to the Professional Engineers Act
These web pages have been updated to include both
enacted and pending changes due to the Open for Business Act, 2010. Note
that some changes will not be in force until proclaimed by the Lieutenant
Governor; for example, the putting into force the end of the industrial
exemption has been delayed numerous times.
Disclaimer
All information on this website is provided without any warranty to its correctness.
The material on these pages reflects Douglas Wilhelm Harder's best judgment in
light of the information available to him at the time of its preparation. Any
use which a third party makes of these pages, on any reliance on or decision to
be made based on it, are the responsibility of such third parties. Douglas W. Harder
accepts no responsibility for damages, if any, suffered by any third party as a result
of decisions made or actions based on these pages.
A set of PowerPoint slides are available at Precedent_Cases.pptx, but
the reader is advised that the discussion related to the presentation is just as important as the slides themselves.
The precedent cases listed here include those on the following topics:
Liability for the Tort of Negligence
Donoghue v. Stevenson, 1932, House of Lords
Ms. Donoghue and her friend entered an establishment where her friend
purchased a sundae with a ginger beer which came in a opaque bottle.
Ms. Donoghue poured out some of the
beverage and drank it with the sundae. When her friend poured her glass,
a decomposed snail came out of the bottle and Ms. Donoghue became sick
as a result. Ms. Donoghue did not purchase the drink so no contract existed
between her and the owner of the establishment and no contract existed
between her and the manufacturer. The snail was not deemed to have been
intentionally placed into the bottle by the manufacturer and therefore by
the laws of the time, the manufacturer could not be held liable in tort.
The House of Lords, however, decided that the defendant did owe a duty
of care to the plaintiff and thus this case introduced the unintentional
tort of negligence.
References: Marston, p.42, wikipedia, Leeds.
Hedley Bryne v. Heller, 1964, House of Lords
The plaintiffs had, without contract, requested information about a
client from their bank. On the favourable report provided by Heller,
the plaintiff extended additional credit for advertising for the client.
This resulted in a £17,000 loss for the plaintiff.
The court found that a negligent but not fraudulent
misrepresentation may give rise to a financial loss even if there
was no contract between the advisor and the advisee. If the advisor
has a special skill which is being relied upon by the advisee, the advisor
has a duty of care to the advisee.
The only mitigating factor was that the defendant had expressly
stated that the information was being given "without responsibility".
References: Marston, p.pp.42-43, wikipedia, UBC.
Wolverine Tube (Canada) Inc. v. Noranda Metal Industries Ltd. et al., 1994, Ontario
An environmental audit and assessment for a property was prepared by
a defendant for Noranda Metal Industries Ltd. The report included the
disclaimer that the report was prepared for Noranda and accepted
no responsibility for damages by any third party who may rely upon
that report. The property was sold to Wolverine Tube (Canada) Inc.
and the audit and assessment was shown to the buyer who relied upon
its content. Later, the property was found not to be as described
and the plaintiff sued for negligent misrepresentation.
The courts upheld the disclaimer of responsibility which appeared
at the top of the document.
References: Marston, p.43-44.
Fundamental Breaches and the "True Construction" Approach
Harbutt's Plasticine Ltd. v. Wayne Tank and Pump Co. Ltd.,
1970, Court of Appeals
The plaintiff entered into a contract with the defendant to perform
an installation in a factory. The contract limited the liability of the
defendant to £2300; however, during the installation, the defendant
installed a pipe which was "thoroughly" and "wholly" unsuited for its
intended purpose which resulted in a fire costing the plaintiff
£170,000. Lord Denning found that the defendant had
fundamentally breached the terms of the contract and therefore could
not rely on the limitation clause within the contract.
This case introduced the concept of fundamental breach.
References: Marston, pp.155-156.
Photo Production Ltd. v. Securicor Transport Ltd., 1980, House of Lords
The defendant entered into a contract with the plaintiff to provide
security services. The contract claimed no liability for any actions
of the employees. An employee started a fire which cost the plaintiff
£615,000. The plaintiff claimed a fundamental breach and
therefore the limitation clause could not be relied upon by the defendant.
The House of Lords found in favour of the defendant.
References: Marston, pp.156-157, wikipedia, BAILII.
Hunter Engineering Co. Inc. v. Syncrude Canada, Ltd., 1989, Supreme Court of Canada
The plaintiff had a contract with the defendant to supply gear
boxes. The contract had expressed warranties but also excluded all
other warranties including any statute warranties. When the gear
boxes broke prematurely and had to be replaced at great cost to the
plaintiff, the plaintiff claimed a fundamental breach.
The Supreme Court ruled that when an exemption clause is clearly
stated, it should be followed. It was suggested that the doctrine
of fundamental breach be "put to rest".
References: Marston, pp.161-162, wikipedia, LexUM.
Tercon Contractors Ltd. v. British Columbia (Transportation and Highways), 2010, Supreme Court of Canada
The defendant had entered into a "Contract A" with the plaintiff
where the bidding was explicitly restricted to six proponents who had
participated earlier on in the process. The contract was eventually
awarded to one of the six parties who had entered into a joint partnership
with another corporation. The plaintiff asserted that this was a fundamental
breach of the contract and therefore the limitation clause should not
be relied upon.
In its decision, the Supreme Court of Canada stated that "With respect to the appropriate framework of analysis the doctrine of fundamental breach should be 'laid to rest'."
References: LexUM.
Bid and Tender Contracts: "Contract A"
Imperial Glass Ltd. v. Consolidated Supplies Ltd., 1960, British Columbia Court of Appeals
The defendant/offeror of a contract made a unilateral mistake in a
calculation for a price. The offeree was aware of this mistake but
chose to accept the contract. The court found that while there may have
been moral and ethical questions with respect to the conduct of the offeree,
the behaviour was not determined to be fraudulent and consequently the
contractor was not relieved of his contractual obligations.
References: Marston, p.116.
Compare this case with the next where only a bid was made.
Belle River Community Arena Inc. v. W.J.C. Kaufmann Co. et al. , 1977, Ontario High Court of Justice
In this case, the defendant submitted a bid of $641,603 which was
$70,000 lower than intended. The defendant realized the error and
attempted to withdraw the bid; however, the plaintiff accepted the
bid and when the defendant did not accept the offer of the contract,
the plaintiff went with the next lowest bidder and attempted to sue
the contractor for the difference.
The court held that no contract existed between the plaintiff and
the defendant and therefore there was no legally enforceable agreement.
References: Marston, pp.116-118.
Ron Engineering et al. v. The Queen in right of Ontario et al., 1981, Supreme Court of Canada
This is a case where the submission of a bid was combined with all the elements of a contract including consideration. The bid
was submitted with a $150,000 deposit cheque. The bid of $2,748,000, however, was determined to be $750,058 lower than intended
as the result of a unilateral mistake on the part of the plaintiff who was attempting to withdraw from the bidding process.
The tender documents included a term that if a tender was withdrawn, the defendant could retain the deposit. The plaintiff attempted
to argue that this case was similar to the previous Belle River case, but in that case, no contract existed. In this case,
the court determined that the tendering process was itself a separate contract from the resulting construction contract.
It is an interesting quirk of history that the court appears to have referred to the tender contract as "Contract A" and the resulting
construction contract as "Contract B" to distinguish the two (no different than a report using the terms Figure 1 and Figure 2).
The consequence, however, has been that in much of the literature since, rather than referring to the tender contract by an appropriate
name, it is referred to as "Contract A".
References: Marston, p.119-120 and 121-122, wikipedia, LexUM.
Equitability in Contracts
Conwest Exploration Co. Ltd. et al. v. Letain, 1963, Supreme Court of Canada
The optionor owned mining claims and the optionor had to take certain steps including incorporation by a given date in order to
exercise the options. Before the date, the optionor (the defendant) implied that the date could be extended. Upon this
gratuitous promise (as it was offered without consideration), the optionee continued to take the steps towards incorporation.
Afterward, the optionor attempted to revert to the strict date provided in the contract. The optionee applied for relief
on the grounds of equitability.
The court found that that it would inequitable to revert to the strict interpretation of the contract and therefore
estopped the optionor from enforcing the date.
References: Marston, pp.92-93, LexUM.
John Burrows Ltd. v. Subsurface Surveys Ltd. et al., 1968, Supreme Court of Canada
The contract the defendant agreed to pay back a borrowed sum of $42,000 over nine years and 10 months at 6% annual interest in
monthly payments. The contract had a clause that if a payment was more than 10 days late, the whole amount payable would
become immediately due.
Out of the following 18 months, eleven payments had been accepted more than ten days after they were due; however, on December
7th, 36 days after the November 1st payment was due, the defendants demanded full payment of the $42,000 with interest. At this
point, the defendant set a registered letter indicating that the plaintiffs were in default and that the defendants were
exercising the clause. The plaintiffs attempted to pay both the November and December payments, but this was refused.
The issue here is that in setting up a pattern of accepting late payments, defendants were essentially setting up a
situation where the plaintiffs would fall into the habit of submitting late payments thereby allowing the
defendants to enforce the default clause at their whim.
The appellate court found this to be a question of equitability and therefore estopped the defendants from enforcing the clause
in the contract; however, the Supreme Court found that equitable estoppel requires a communication between the parties must occur:
the passive acceptance of payments did not imply any form of consideration; the Supreme Court quoted the trial judge, "I do not believe that John Burrows ever gave
any consideration to the fact that in accepting late payments of interest..., he was thereby leading Mr. Whitcomb into thinking that
strict compliance would not be required at any time." and the dissenting voice, Bridges, of the Court of Appeals, "For estoppel to apply,
I think we must be satisfied that the conduct of Burrows amounted to a promise or assurance, intended to affect the legal relations of the
parties to the extent that if an interest instalment became in default for ten days the plaintiff would not claim the principal as due unless
it had previously notified the defendants of its intention to do so or, if it had not so notified them, that notice would be given them
the principal would be claimed if such instalment so in default were not paid. This is, I think, a great deal to infer." Consequently,
for equitable estoppel to arise, it requires the active participation on the part of the party making the gratuitous promise.
References: Marston, pp.93-95, LexUM.
Owen Sound Public Library Board v. Mial Developments Ltd. et al., 1979, Ontario Court of Appeals
The contract stipulated that the owner/plaintiff was to honour payment certificates issued by the architect within seven
days. With one payment certificate, the plaintiff requested that a document supporting the payment certificate
be sealed by the relevant sub-contractor. The defendant agreed but did not obtain the seal until after the
seven-day time limit passed.
The contractor attempted to claim a breach of contract and the plaintiff brought the case to court on a question
of equitability. The count found that as it was the actions of the contractor which caused the owner to default,
they estopped the defendant from enforcing the strict terms of the contract.
References: Marston, pp.95-96.
Implied Terms in Contracts
The Moorcock, 1889.
The Moorcock was a ship, the owner of which had a contract with a dock to moor
the ship for unloading. The ship was moored and when the tide went out, the ship struck
bottom and was damaged. The contract did not have an obligation that the ship would be
safe during the time it was docked.
The judge, however, determined that under such a circumstance, it would be an
implied term in the contract that the ship should, under normal circumstances,
be safe while moored. The judge only allowed for implied terms when
in all events as it must have been the contemplation of both parties.
References: Marston, p.137, wikipedia.